Episode Transcript
Available transcripts are automatically generated. Complete accuracy is not guaranteed.
(00:00):
.9998474121Welcome to Major Project Podcast.
2
00:00:01,659.9998474121 --> 00:00:10,139.999866486
We're here to talk about some of the biggest projects in the world, how they get done, talking with leaders that have been on the ground understanding this amazing space.
3
00:00:10,139.999866486 --> 00:00:12,699.999332428
So today with me is Matt Mitchell.
4
00:00:13,0.000476837 --> 00:00:14,590.001087189
He works, in capital projects.
5
00:00:14,590.001087189 --> 00:00:23,789.99994278
He is a certified risk management professional with over a decade of experience in risk, project controls across energy and industrial sectors.
6
00:00:24,199.999790192 --> 00:00:34,950.000553131
So, his prior job, he was at Noble Energy leading ri- risk management initiatives, and now he is working at Electrical Grid Monitoring, which is a new venture focused on innovative power line sensors.
7
00:00:35,359.999637604 --> 00:00:37,449.999790192
Matt is also a member of Mints International.
8
00:00:37,449.999790192 --> 00:00:40,29.997806549
He's got real great analytical rigor.
9
00:00:40,299.998264313 --> 00:00:46,310.000400543
We've had some great conversations around solving challenging problems in capital projects and risk assessments.
10
00:00:46,310.000400543 --> 00:00:47,909.998874664
I'm excited to bring them to you today.
11
00:00:48,219.999485016 --> 00:00:50,170.000247955
Matt, welcome to the podcast.
12
00:00:51,170.000247955 --> 00:00:51,820.001773834
Thank you, Orion.
13
00:00:51,870.001773834 --> 00:00:52,380.000095367
Thanks, Matt.
14
00:00:52,380.000095367 --> 00:00:58,470.000247955
And before we get started, maybe you can just give us a little bit of your history and how you got into working in major projects.
15
00:00:59,640.001468658 --> 00:01:09,239.999027252
I actually started off more on the technical side IT and software development, and I, got into risk management with a couple of different things that I did.
16
00:01:09,239.999027252 --> 00:01:12,870.003910065
First, I worked at Enron, and we had some formal training around risk management.
17
00:01:13,460.000247955 --> 00:01:18,649.995059967
But then I worked for a software company that had a really strong risk management platform.
18
00:01:19,209.992618561 --> 00:01:32,170.006046295
And so we were rolling that out to various customers and doing a lot of, prospecting, of what risk management would look like and what the global risk management system would do, and ended up going to work for one of our customers.
19
00:01:32,640.007266998 --> 00:02:10,34.00880174
And as we rolled out this global risk management system, they realized they didn't have anybody to manage it, and so that became my role, and th- eventually started working on a variety of their con- construction type projects and, you know, oil and gas type stuff, and, took on the role of risk lead and ended up with some of the very large projects that they had It's interesting to go from the software side because when I look at the project control space and the software space, I feel like risk is probably the one area that I've seen more often than not managed from small to really large enterprises in Excel.
20
00:02:10,374.00704698 --> 00:02:18,604.00582628
So you're really in a interesting niche to come from s- a software solution that focuses on risk, and then rolling it out broadly.
21
00:02:18,604.00582628 --> 00:02:31,494.01093797
Did you, do you find that's true as well in your experience? But what is interesting about it is that for risk management, you know, you think of just any kind of software at large, the software has to do whatever the company's business process is.
22
00:02:32,104.01154833 --> 00:02:42,314.0106328
But with risk management, we have some pretty good guidance out there, ISO 31000, we've got Project Management Institute, that all kind of lay out this framework of what you should be doing for risk management.
23
00:02:42,714.00834398 --> 00:02:45,964.00834398
And so the software was built to, to do those things.
24
00:02:45,994.01093797 --> 00:02:51,134.01080446
As I understand it, we also are gonna get to talk a little bit about the Leviathan Project.
25
00:02:51,414.01101427 --> 00:02:57,264.01044206
You know, public information only, of course, but this was a large gas field project in Israel.
26
00:02:57,264.01044206 --> 00:03:02,654.01173906
And so maybe you can tell us a little bit about that and your role on the Leviathan Project.
27
00:03:02,934.01166277 --> 00:03:07,24.01181535
It's a very large project that takes many years to develop.
28
00:03:07,24.01181535 --> 00:03:16,534.00723772
It's interesting with the backdrop of what's going on in world, geopolitical things today that, these projects are decades in the making in some cases.
29
00:03:16,534.00723772 --> 00:03:20,214.00449114
You have people on and off, and a lot of, knowledge gaps here and there.
30
00:03:20,214.00449114 --> 00:03:40,334.01700334
So risk management is crucial because as projects get mothballed or delayed or scope changes or even the entire concept changes, the capturing of that information and the risks that we considered and the reasons why we made certain decisions that we made, those should be documented and documented well.
31
00:03:40,334.01700334 --> 00:03:42,494.02066545
And risk management is one of the best ways to do that.
32
00:03:42,644.02219133 --> 00:03:48,614.02676897
We consider doing this, we said the cost was too much for that, we chose a different concept, but those things change over time.
33
00:03:48,644.02554826 --> 00:03:59,34.02951555
So, you know, these huge projects, risk management is a key part of the entire life cycle of the project, even up until the point where the project might get canceled.
34
00:03:59,224.02432756 --> 00:04:04,874.02585344
You know, somebody might pick it up again five years down the road, and it's gonna be important to understand what took place.
35
00:04:05,794.02402239 --> 00:04:07,254.02310686
Well, so tell us about Leviathan.
36
00:04:07,304.02493791 --> 00:04:14,424.0276845
What was the project and when did you intersect it? And then your role was risk, so just give us a little background there.
37
00:04:14,654.02646379 --> 00:04:26,574.02615862
So, it started off, you know, it was pretty far offshore, and it started off as a floating, production, FPSO, float- floating production basically a ship.
38
00:04:27,334.02066545 --> 00:04:32,684.02676897
And so that concept was kind of battered around for, I think, a couple of years.
39
00:04:33,224.02310686 --> 00:04:42,114.02249651
And then it ultimately based on some of the s- the, successes of the other two platforms that had been put in it became a very large platform a little closer in.
40
00:04:42,664.02860002 --> 00:04:46,214.03165178
And, and so that was the, that was the final investment decision.
41
00:04:46,844.03958635 --> 00:05:03,178.03779344
But, you're talking about years of research that led into that, and so I became- this? That was around 2000- 14, 15- Was that FID? So it was not long after Tamar went in, which was, I believe, 2013.
42
00:05:04,28.03817491 --> 00:05:13,548.03844194
So the concept, kind of shifted to using Tamar as part of the whole system of production, versus just having the ship do everything.
43
00:05:14,88.03859453 --> 00:05:20,328.03836565
I got into that project around the 2015 timeframe, '15 or '16, I believe.
44
00:05:21,58.03790788 --> 00:05:27,638.04050188
And that was, right around the time that they made final investment decision and sanctioned that project as that large, platform.
45
00:05:27,668.03928118 --> 00:05:29,658.03714494
So massive platform, in fact.
46
00:05:29,658.03714494 --> 00:05:30,918.03760271
So quite fascinating.
47
00:05:31,648.03714494 --> 00:05:37,258.0339406
So how big was the project when it FID'd? I believe at FID, it was about 3.8
48
00:05:37,258.0339406 --> 00:05:38,478.0351613
or 3.9,
49
00:05:38,478.0351613 --> 00:05:39,78.03363542
something like that.
50
00:05:39,128.03363542 --> 00:05:39,478.03210954
Okay.
51
00:05:39,848.03104143 --> 00:05:40,188.03500871
Great.
52
00:05:40,638.03195696 --> 00:05:46,308.0301259
And then your role, so you intersected right around FID, right after.
53
00:05:46,698.03256731 --> 00:05:47,858.03622942
So what did you...
54
00:05:47,858.03622942 --> 00:05:51,568.03531389
And you came in as a, as a risk lead.
55
00:05:51,568.03531389 --> 00:05:52,518.03226213
Is that right? Risk, yeah.
56
00:05:52,688.03806047 --> 00:06:08,928.04392557
So did you, when you started that job did you inherit- The risk register and like how did you approach risk right at that FID point? 'Cause that's a very interesting point when a project goes from, you know, are we doing this to like, we are doing this.
57
00:06:09,358.04423075 --> 00:06:20,178.04468851
But you really wanna honor all the risk work that's gone on in the past, but you're also new to this job, Walk me through how you navigated that, 'cause that's kind of a complicated little s- point to intersect a project.
58
00:06:20,238.04415445 --> 00:06:24,278.04201822
It's interesting because, obviously every company's different, every project is different.
59
00:06:24,758.04156046 --> 00:06:30,868.03988199
But the better developed and the more mature that risk management process is, the easier it is to do something like that.
60
00:06:30,898.03866129 --> 00:06:41,338.04323892
So in my role at that time we were working from only kind of what we had seen with the previous platform, and let's take that risk register and we'll repurpose it, and it'll kinda...
61
00:06:41,338.04323892 --> 00:06:43,998.03927164
Some of these apply, some of these don't, and go forward with that.
62
00:06:44,398.04079752 --> 00:06:49,298.04156046
But we eventually, this was such a large project, it had so many, aspects of it.
63
00:06:49,668.03667764 --> 00:06:57,568.03515177
We eventually ended up running two different risk registers because we had so much that was on the commercial side of things, and then there was the project execution.
64
00:06:57,568.03515177 --> 00:06:59,338.03637247
And, and when you, when you, kinda...
65
00:06:59,638.04247598 --> 00:07:07,178.04339151
the overlap of those kind of muddies the water a little too much for the project team, so we just really wanted to focus on project execution.
66
00:07:07,178.04339151 --> 00:07:12,438.04552774
What's gonna, what's gonna impact the project, and don't worry about the commercial aspects of it.
67
00:07:12,438.04552774 --> 00:07:13,458.0498002
We'll manage that separately.
68
00:07:13,458.0498002 --> 00:07:28,848.0494998
So you were able to kind of like bifurcate the risk register that you received, and then focus, target more in on execution risk rather than get involved in maybe the more complex commercial risks, which might have been the bigger focus pre-FID anyhow.
69
00:07:28,848.0494998 --> 00:07:29,8.04934721
Right.
70
00:07:29,8.04934721 --> 00:07:29,638.05041532
That's smart.
71
00:07:30,308.04972868 --> 00:07:30,558.04972868
Yeah.
72
00:07:30,558.04972868 --> 00:07:51,668.04957609
You know, like it's public information that, you know, they're selling gas to Egypt, right? And it's almost like maybe some of that risk involving maybe geopolitical things is a different discipline in some respects than- Yes engineering risk, which maybe is a little bit more quantitative, like, and can be defined a bit differently.
73
00:07:51,668.04957609 --> 00:07:52,588.05155973
So that seems...
74
00:07:52,638.05079679 --> 00:07:52,918.04957609
yeah.
75
00:07:53,548.04988127 --> 00:07:54,908.05049162
I should probably back up.
76
00:07:55,48.04911833 --> 00:08:04,258.04362516
So maybe we can just define when we talk about project risk on a major project, can you kind of take us through a little bit of a 101 on that and just kind of get...
77
00:08:04,258.04362516 --> 00:08:10,618.04881315
give us a refresher even for the advanced project people? Because it's such a niche space, I think it's always good to go back and, and just learn.
78
00:08:10,618.04881315 --> 00:08:11,938.04850797
So tell, tell me about risk.
79
00:08:12,488.04393034 --> 00:08:21,758.0405734
What is risk? The ISO definition of risk risk is the effect of uncertainty on our objectives where that uncertainty is a deviation from what we expected.
80
00:08:21,918.03752165 --> 00:08:24,868.04209928
That's the textbook definition from a project perspective.
81
00:08:25,698.04393034 --> 00:08:30,128.04423551
So what that means is we have to consider all of the objectives of the project.
82
00:08:30,158.04301481 --> 00:08:35,198.03172331
What are we trying to do? You know, of course, CD cost schedule, and, and time.
83
00:08:35,838.03111296 --> 00:08:43,268.02378874
But it's most effective to boil those things down into what's the effect on the schedule, what's the effect on the cost.
84
00:08:43,818.02684049 --> 00:08:58,138.01890592
Yes, you'll find things that are, are effects on health and safety and environmental and all, but those, those are, are sometimes hard to kind of quantify, hard to mitigate and, sometimes again muddy the water around what are the objectives of the project.
85
00:08:58,138.01890592 --> 00:09:04,958.02623014
So focus on those objectives, identify what things could happen to prevent us from achieving those objectives.
86
00:09:05,398.02867155 --> 00:09:18,728.01829557
Or if something bad were to happen, what would we do to get it back on track to make that objective? So that, that is what risk management is just trying to make sure that we prevent the things that might not allow us to achieve the project objectives.
87
00:09:20,760.02439819 --> 00:09:22,180.02443724
And then does that also...
88
00:09:22,240.02437048 --> 00:09:36,970.02551489
so does risk also include the upside, managing that deviation from an expected outcome? And so that's, it's an interesting perspective because the COSO ERM framework says that your objective is your objective.
89
00:09:37,60.02566748 --> 00:09:41,530.02398901
If you come over or under that's, either of those is a risk and should be considered.
90
00:09:41,950.02520971 --> 00:09:53,990.02498083
W- whereas PMI and, and others, in essence, they say, you know, if you come over the, you know, like if your production target is 100 barrels and you come in at 150, that's an opportunity.
91
00:09:54,580.02513342 --> 00:10:06,950.02360754
But e- the, I, I kind of prefer the COSO perspective because it makes you think, "If I come over, you know, 150, can my production handle it?" So the COSO ERM is a good perspective.
92
00:10:07,400.02437048 --> 00:10:08,480.02620153
This is what we wanna get.
93
00:10:08,840.02681188 --> 00:10:12,480.02620153
If we go over, we have to consider what risks might occur there.
94
00:10:12,720.0240653 --> 00:10:39,428.031427
If we come under, we have to also consider, what risks could occur and what the commercial aspects of it are What I'm hearing is risk management is always has a time component in a way, 'cause it's like if we're at time T zero and you pick a point out here at T 10 or whatever and you, you also have this observer, a frame, where you're like, "By these mechanisms, this should be here."
95
00:10:39,848.03150329 --> 00:10:56,128.02936706
And then risk is saying what is the actual deviation from expected, like- So there's always an element of there's a time horizon that you have to be considering, and then you also have to be considering whose perspective are you looking at for that risk.
96
00:10:56,558.02967224 --> 00:11:00,548.03211364
Is there always one? We talk about risk registers, it's like that's your list of risks.
97
00:11:00,548.03211364 --> 00:11:06,58.03043518
You kind of have to have alignment, right? If, if people don't understand what the goal is, you can't really tell them the deviation from that goal.
98
00:11:06,318.03562316 --> 00:11:07,898.02982482
Right how do you...
99
00:11:08,228.03165588 --> 00:11:10,238.03379211
Is that the risk manager's job, or is that...
100
00:11:12,38.03226623 --> 00:11:13,408.03501281
you have to get beyond the bias.
101
00:11:13,408.03501281 --> 00:11:18,438.03379211
You talk through what the risks are, things that might occur and you often get the, "Oh, yeah, that'll never happen.
102
00:11:18,438.03379211 --> 00:11:19,738.03684387
I, we've never seen that."
103
00:11:19,738.03684387 --> 00:11:22,608.03959045
Or, or the opposite is, "Oh, we have to...
104
00:11:22,648.04050598 --> 00:11:26,518.03562316
You know, we need to order 12 extra valves because we're gonna have so many fail."
105
00:11:26,988.03989563 --> 00:11:29,178.04233703
So you, you kind of talk them through.
106
00:11:29,178.04233703 --> 00:11:35,638.0414215
The, the valve one is a good example where we had an engineer that said, you know, we're ordering eight or 10 or 12 valves.
107
00:11:35,638.0414215 --> 00:11:38,358.04264221
I don't know how many it was, but you know, we're talking about risk.
108
00:11:38,358.04264221 --> 00:11:39,278.04081115
He said, "Oh, yeah, the...
109
00:11:39,278.04081115 --> 00:11:43,138.0414215
It's an ex- extremely high likelihood that, that we're gonna, they're gonna fail.
110
00:11:43,328.04691467 --> 00:11:43,748.04508361
Very high."
111
00:11:44,268.04935608 --> 00:11:46,548.04813537
And so I said, "Well, okay, you know, we're putting this in the risk register.
112
00:11:46,548.04813537 --> 00:11:49,288.04599914
And it's gonna be at the top of the list if it's a very high likelihood."
113
00:11:49,338.04599914 --> 00:11:54,828.03928527
I said, "Okay, well, if you ordered 100 valves, how many of them would you expect to fail?" probably three."
114
00:11:55,248.03745422 --> 00:12:02,248.03745422
"Okay, that's a very low probability of, of that failure occurring, so, you know, we put it in at, at very low in the risk register."
115
00:12:02,248.03745422 --> 00:12:12,788.04599914
So it's about having that conversation and talking them through and, and making them think about is this really a risk or, you know, have I considered all the things that, that could occur.
116
00:12:13,628.04233703 --> 00:12:17,738.04294738
Well, maybe that gets into that term I think we've heard, a, a black swan.
117
00:12:17,838.0490509 --> 00:12:18,648.04660949
Like, how do you...
118
00:12:19,118.05088195 --> 00:12:21,278.05454406
so maybe t- talk about black swan.
119
00:12:21,278.05454406 --> 00:12:30,580.05319849
Is that actually in a defined ISO term, or is it just sort of something we've come up with? That it's so, outrageous that we can't...
120
00:12:30,850.05270258 --> 00:12:37,630.05357996
we shouldn't even consider it because there's nothing we could do about it if it occurred, and there's nothing we could do about to, to prevent it from occurring.
121
00:12:38,90.05380884 --> 00:12:39,480.05510584
But yeah, there...
122
00:12:40,250.0555636 --> 00:12:48,560.05045191
You have to focus on what you can control and what reasonably will impact the project, and that's the word that I use cannot reasonably occur.
123
00:12:48,830.05090967 --> 00:12:57,490.04999414
Otherwise we're, you know, we're gonna waste a lot of money and waste a lot of time thinking about things like, planes crashing and things that, are very unlikely to occur.
124
00:12:58,490.0492312 --> 00:13:16,970.05335108
So you did risk management for broad portfolio I believe for a large company, and you were managing small project risk and then really large project risk, and sort of how do you make risk economical? 'Cause I think sometimes as, like, an executive, you're gonna be looking at this saying, risk management...
125
00:13:16,970.05335108 --> 00:13:19,320.0518252
Like, the risks are probably gonna occur anyhow.
126
00:13:19,970.05335108 --> 00:13:25,400.05365625
I could spend millions of dollars trying to prevent that one in 1 million thing.
127
00:13:25,640.05914942 --> 00:13:27,430.05243555
You know, how do you properly...
128
00:13:27,490.0530459 --> 00:13:37,730.05090967
what's the right economic model to look at risk so that you're spending the right amount and being, you know, a, a good sort of steward of the funds of a project? What...
129
00:13:38,50.05060449 --> 00:13:52,610.03473535
How do you balance that? Every project is different, and one of the things that, I feel like some project teams get, twisted up on is that the company might have a global risk matrix or a corporate risk matrix, but the project has to have its own.
130
00:13:52,740.03961817 --> 00:13:56,650.04328028
And, generally, that's going to be in terms of the cost and schedule impacts to that project.
131
00:13:56,730.04205957 --> 00:13:57,760.04083887
You know, is it, is...
132
00:13:58,120.04144922 --> 00:14:18,290.04114405
Do you do the matrix at, you know, 10%, 25%, 50%, 75%, 100%, budget impact? That, that lets you frame that project in terms of its biggest risks and, you know, compare it to other projects of similar sizes or, you know, that a big risk on a million-dollar project might be $100,000, but a big...
133
00:14:18,560.03015772 --> 00:14:24,100.0417544
But $100,000 risk on a billion-dollar project is really, you know, has a different frame of reference.
134
00:14:24,100.0417544 --> 00:14:31,90.03504053
So, the risk matrix is the important way to differentiate big risks on different projects.
135
00:14:32,746.02954811 --> 00:14:41,276.0285849
And then you rolled out, I believe as well, as part of managing a global portfolio you rolled out a training program, is that right? So when you...
136
00:14:41,566.02873749 --> 00:14:44,346.02965302
but what would you say when you gave those...
137
00:14:44,726.02881378 --> 00:14:52,376.03033966
'Cause w- who was your audience with that? It was like project, project control managers, the engineers, you know, folks involved in the, the project.
138
00:14:52,376.03033966 --> 00:15:01,80.0298056
Like what- What do you think were some of the aha moments or things that you gave these people when you were doing risk training, in 2000? Yeah.
139
00:15:01,130.0298056 --> 00:15:03,320.03033966
We used the term risk champions.
140
00:15:03,360.03030151 --> 00:15:14,920.03091187
A- and what that meant was people who kind of understood and had an interest in knowing more about what project risk management looked like, that we could go out and teach them and then let them go do.
141
00:15:14,970.03091187 --> 00:15:16,130.03075928
So that worked really well.
142
00:15:16,180.03075928 --> 00:15:23,0.02877564
It's hard to do it all as a single individual, and risk management is all about everybody understanding how the whole process works.
143
00:15:23,0.02877564 --> 00:15:26,650.03228516
So we just tried to teach everyone that we could and find interested people.
144
00:15:27,320.0304541 --> 00:15:28,960.03060669
But, yeah, it was a variety of folks.
145
00:15:28,960.03060669 --> 00:15:32,850.02999634
Project controls, engineers, a lot of coordinators.
146
00:15:33,460.03060669 --> 00:15:49,240.03014893
So if somebody was listening to this and they were like, "I wanna set up something like that for my company," what would you advise them in terms of, like, leveling up risk? 'Cause it sounds like it's not just hire the perfect risk manager, it's actually something that has to be baked within the organization.
147
00:15:49,240.03014893 --> 00:15:52,350.03075928
It, sort of it organically, kind of like safety.
148
00:15:52,730.03564209 --> 00:15:54,820.03960938
You know, you don't get safe- you have to have a safety culture.
149
00:15:54,820.03960938 --> 00:15:57,630.03716797
It sounds like you worked on creating a risk culture.
150
00:15:58,90.0393042 --> 00:16:01,320.03503174
Yes how do you create that? It's just about getting in there and doing it.
151
00:16:01,320.03503174 --> 00:16:10,710.03991455
Like, get in and start a risk register and, you know, begin working through what that whole process looks like who should be involved.
152
00:16:10,710.03991455 --> 00:16:23,150.03625244
And the first risk workshop is the hardest, and after that it starts to become a little bit more mechanical and people know what they're expected to do, and you can do a lot of, prep work up front before you get into the workshop.
153
00:16:23,150.03625244 --> 00:16:29,400.03625244
So it's just a matter of getting in and starting to do it, and then making it better every chance you get.
154
00:16:31,70.03442139 --> 00:16:32,930.03503174
Okay, so risk workshops.
155
00:16:33,80.02892822 --> 00:16:35,240.03259033
Maybe we can go back to Leviathan real quick.
156
00:16:35,390.02953857 --> 00:16:41,140.0325903
I'm assuming day one you had a risk workshop to kind of, start that process.
157
00:16:41,678.0258756 --> 00:16:56,958.0255904
Maybe talk to, tell us the story of the first risk workshop on Leviathan or, like, how did, how did you create that process and So it was the first workshop, yes, it was a little awkward because it was kind of the first time that team had come together to talk about risk registers.
158
00:16:56,958.0255904 --> 00:17:04,478.0279555
And, the risk workshop, the whole idea is that everybody understands what those risks are and what they mean, even if they don't have anything to do with it and it's not their discipline.
159
00:17:05,38.0274214 --> 00:17:16,238.0258955
And so, you know, you have a lot of vocal voices and, y- that- that's half the role, is being able to kind of manage those personalities and, "Yeah, we'll ta- Yes, let's put that in the parking lot.
160
00:17:16,238.0258955 --> 00:17:17,448.02498
We'll, we'll take that offline.
161
00:17:17,448.02498 --> 00:17:18,558.0255904
We'll talk about it later.
162
00:17:18,868.025743 --> 00:17:20,538.0277266
Yeah, yes, that's a valid risk.
163
00:17:20,938.0292525 --> 00:17:25,938.0284895
Let's, we considered it and, here are the mitigations and here's why we don't think it's gonna happen."
164
00:17:26,418.0289473 --> 00:17:31,498.0269637
But then, you know, once the team is, is used to doing the workshop together, it goes pretty smoothly.
165
00:17:33,38.0278792 --> 00:17:34,958.0260481
So tell me about the personality management.
166
00:17:35,48.0300154 --> 00:17:35,468.0281844
Like, what...
167
00:17:35,588.0309309 --> 00:17:45,742.0265509
That's, that gets out of the comfort zone of the numbers and into something a little more- you know, probably a little more real about how real work gets done.
168
00:17:45,782.0265509 --> 00:17:46,152.0264365
Yeah.
169
00:17:46,652.0264365 --> 00:17:59,252.0278479
You know, It's, it's- Yeah it's back to the comment about the psychologist, right? Not only do you have to, manage the loud personalities, but you have to coach the quiet ones as well and, what the term they use is elicit risk.
170
00:17:59,402.0274664 --> 00:18:16,152.0296027
Get them to tell you what is it that they're thinking and then kind of understand that and present it back to them as the, "Are you saying that this could occur?" Or, "Are you saying that we need to do this?" So it's a lot of, working with people and people management tell me more about that.
171
00:18:16,272.0285345 --> 00:18:18,462.0271612
'Cause so you brought in people in the field.
172
00:18:18,492.0297552 --> 00:18:18,552.0273138
Right.
173
00:18:19,122.0270087 --> 00:18:23,882.0291449
So it wasn't just the corporate office, 'cause they're the ones that really are getting the project done.
174
00:18:25,372.0300604 --> 00:18:25,852.0296027
Me what...
175
00:18:25,932.0314337 --> 00:18:35,512.0227362
How was that? Yeah, and that's another big challenge you face is you've got these experts from the field which are necessarily there, but they don't wanna be there.
176
00:18:35,562.025788 --> 00:18:45,2.0151068
You have to be considerate of their time, do as much, upfront work as you can to make that meeting valuable the whole time they're there and meaningful the whole time they're there.
177
00:18:45,32.0138861 --> 00:18:47,842.0114447
And again, that also goes back to the, the people management.
178
00:18:47,842.0114447 --> 00:18:50,382.0123602
Don't let just the one person rule the whole meeting.
179
00:18:50,432.0163275 --> 00:18:53,912.0196844
We need to get all the opinions and have all the conversations.
180
00:18:53,992.0184637 --> 00:19:04,272.017243
One example, we went into a risk workshop and the leader of the entire group said, "You guys are here today to tell me why X is our biggest risk."
181
00:19:05,212.012055 --> 00:19:06,312.0181586
conducted the workshop.
182
00:19:06,422.0111395 --> 00:19:11,882.0178534
Everybody had their input, and X came out as the third-biggest risk from that group.
183
00:19:12,2.0129706 --> 00:19:20,732.0193793
So it's about having those conversations and everybody else understanding, w- what's his risk or her risk versus mine and my scope.
184
00:19:22,70.0199889 --> 00:19:29,530.0205039
So if you're facilitating a risk workshop, is there like, Is there some sort of like 80 people in a room talking about risk doesn't work? Is there...
185
00:19:30,0.0198173 --> 00:19:34,150.0213432
Like how do you prep the conversation? What's a good...
186
00:19:34,350.0201988 --> 00:19:40,420.021038
Is it like an hour, hour and a half? Like how do you do those? Yeah.
187
00:19:40,450.0198173 --> 00:19:44,570.0187492
Sometimes dependent on the, the size of the project and the experience of the people.
188
00:19:45,20.0195121 --> 00:20:08,860.0150871
What I find m-most useful, of course, what you always want to be able to do is to start from a lessons learned review, whether that's doing it yourself and going through and saying maybe these things apply to this project, and putting them into the risk register, and going and looking at similar projects and seeing what risks they identify or, or experienced, and-- but putting all those into the risk register.
189
00:20:09,270.0187492 --> 00:20:13,360.0227165
And then do as much as you can, upfront interviews with people.
190
00:20:13,390.0214957 --> 00:20:16,490.0199699
You know, give them a call and just say, "Hey, we're doing a risk workshop.
191
00:20:16,490.0199699 --> 00:20:18,0.0221061
Was wanting to get your perspective."
192
00:20:18,0.0221061 --> 00:20:23,790.030651
And, you know, try to get those individual perspectives ahead of the group meeting, and come with something to show them.
193
00:20:24,50.0251579 --> 00:20:31,420.0309562
You know, if you start off the meeting with all those personalities in the room and you got a blank screen and you say, "Okay, what are the risks?" You're, you're destined to fail.
194
00:20:32,50.0282096 --> 00:20:36,60.0333976
So w-we wanna have as much, work done upfront as you can.
195
00:20:36,650.0318717 --> 00:20:43,260.0346183
But so instead of starting with a blank, like everybody list your risks, one, two, three, four, you set up a lessons learned.
196
00:20:43,260.0346183 --> 00:21:00,790.041027
Is that usually around a risk that has triggered or, you know, something like that, so it's gets everyone disarmed to actually talk about risk? Or h-how-- what's the lesson that you share? The, the PMI guidance is that a lesson learned is a future project risk.
197
00:21:01,280.0343131 --> 00:21:07,340.02882
Part of your project, you should be capturing lessons learned on a regular basis and, writing them in a way that it's useful for a future project.
198
00:21:07,810.0300407 --> 00:21:16,800.0318717
And then to start a risk register to kick off a project, you would wanna go and look through the lessons learned from previous projects, especially those that are similar to the one that you're working on.
199
00:21:16,890.0312614 --> 00:21:19,340.0251579
That's always the best starting point if you can do that.
200
00:21:19,480.0245475 --> 00:21:21,590.0282096
Also, previous risk registers.
201
00:21:22,0.0318717 --> 00:21:32,820.0239372
One of the reasons I say don't delete a risk just because it's mitigated or it's no longer applicable, leave it in there and just say that it's closed out because somebody's gonna need to review that sometime in the future.
202
00:21:33,440.02882 --> 00:21:35,970.0245475
You know, that technically would be a lessons learned review.
203
00:21:36,660.0312614 --> 00:21:49,642.053811
So that's a lot of what the homework is to lead up to the workshops And so you said the, the, on Leviathan, the workshop- the first workshop was, was obviously rocky 'cause you're just getting everything started.
204
00:21:49,642.053811 --> 00:22:03,382.0528573
And I imagine myself, let's say I'm a risk manager listening to this podcast, and I just got on a billion-dollar job, and I'm thinking about, what, what do I need to do here? One question I would have is I think everything usually has, like, a rhythm.
205
00:22:03,672.0537729 --> 00:22:11,62.0531625
You know, when you look at, like, risk, safety, you know, any function within an organization, there's sort of like a sine wave of activity.
206
00:22:11,102.0521707 --> 00:22:18,412.0516366
And it seems like those meetings and that sort of regular risk management process is kind of that, that flywheel.
207
00:22:18,592.0511789 --> 00:22:39,446.051465
What's the frequency that you might wanna do it, like monthly, quarterly? What are those activities that help anchor good risk discipline? I'll say, the, the easiest way to dovetail a risk review in is to kind of piggyback on a cost or schedule review, or a cost and schedule review if you can do that.
208
00:22:39,856.0513124 --> 00:22:40,716.0500154
They're all related.
209
00:22:40,836.0508546 --> 00:22:46,426.0510072
And it's easiest since you already have that team assembled to do that review to say, "Hey, let's, let's do risk review after that."
210
00:22:46,636.0500917 --> 00:22:47,46.0499391
Okay.
211
00:22:47,706.0497865 --> 00:23:01,176.0471925
And then how do you deal as the project psychiatrist during that? You know, 'cause cost review, schedule review, oftentimes I find people don't want to identify r- I, I...
212
00:23:01,616.0496339 --> 00:23:19,516.0473451
risk is one of those things that, like you said, there's the quiet folks in the room, but like people oftentimes don't wanna surface risk 'cause there might be political problems with surfacing a risk, and it's actually easier in their world to like let that risk ride, and if it triggers then it's just like, "Hey, this happened."
213
00:23:19,866.0534486 --> 00:23:30,26.0571107
How do you break through that and sort out the political consequences of like raising a risk for someone? 'Cause I think that sometimes keeps the risks unsurfaced.
214
00:23:30,946.0552797 --> 00:23:53,566.0549745
Like do you address that specifically or is that an organic thing? Like, how do you surface risk given that it can create political problems for other people? Maybe it's like, "Why did we ever even order these types of fasteners? Like, who would order something that could rust in, in a storm?" You know, it feels like sometimes risk turns into a witch hunt, and people don't wanna be the one to kick off the hunt, so to speak.
215
00:23:54,396.0568055 --> 00:24:05,906.0513124
What I will say at Noble, w- one thing that their drilling group did an excellent job of was a lesson learned review is not a finger-pointing session, and so everything is on the table.
216
00:24:06,576.0494813 --> 00:24:08,286.0592469
And they're, they were really good at that.
217
00:24:08,286.0592469 --> 00:24:17,376.0555848
And so we, we kind of piggybacked off of that in projects to say, "Look let's implement this really good lessons learned program, and just put everything out there."
218
00:24:17,836.0500917 --> 00:24:26,116.0214051
Once people understood it they knew, yes we c- we're finding faults and things, but w- this is good because we're gonna prevent it from occurring again.
219
00:24:26,196.0354432 --> 00:24:30,746.038495
Yeah, it's, it's again back to the people management aspect of, of getting people to, to talk.
220
00:24:31,136.0378846 --> 00:24:41,306.0360536
And it also, you know, the, the prep t- that you do ahead of time, if you can have a one-on-one with somebody you're more likely to get something like that and say, "Well, here's how we're gonna address it in the big group session."
221
00:24:42,794.0311699 --> 00:24:57,384.0310945
Is there, on a large project, is it that anything that deviates from the expected is either a risk that was documented or a risk that you never knew about, but it all kind of fits into risk in a way? Is that...
222
00:24:58,64.0313997 --> 00:25:11,60.0323533
Because I, I guess m- my question is, what do you do about those risks where something happened in the field and it caused, you know, 1,000,005- deviation on the project, you find out about it.
223
00:25:11,90.0323247 --> 00:25:12,850.0323152
It's, it has nothing to do with the risk register.
224
00:25:12,850.0323152 --> 00:25:15,260.0321626
It was, but it's not a black swan.
225
00:25:15,590.0320863 --> 00:25:27,960.0310182
Like, is there some cleanup activity you have to do to kind of be like, "Okay, this actually was a risk we never caught"? How do you surface those? Like, how does that play in? It's the known unknowns versus the unknown unknowns.
226
00:25:28,180.0314759 --> 00:25:36,420.0331544
It's just that you, you do as much work upfront as you can to try to identify what types of those things might occur.
227
00:25:37,60.0325441 --> 00:25:50,540.0363588
You know, we talked about in the, in the Mediterranean, we had a, a survey go through where the, you know, where the, one of the pipelines was supposed to be laid, and they found some ancient jugs on the, on the sea floor, right? Yeah.
228
00:25:50,980.0349855 --> 00:25:55,540.0363588
But you do the survey for a reason, and so you, you might carry some of those risks just in case.
229
00:25:56,280.0342225 --> 00:26:01,0.0392579
So, it's about thinking through, you know, what, what might go wrong with each of the activities that we have planned.
230
00:26:01,540.0401735 --> 00:26:10,970.0404786
And again, will it truly impact our objectives? We could have a delay and, piece of equipment arriving, but it doesn't impact the schedule.
231
00:26:11,80.0365113 --> 00:26:12,720.035901
It doesn't change our start-up date.
232
00:26:12,920.0404786 --> 00:26:15,760.0368165
So okay, it was delayed a week, that's okay.
233
00:26:15,840.0355958 --> 00:26:26,310.0261354
We might have some cost impact of that, carrying cost or time delay or whatnot, but it doesn't impact the objectives of the project, so it might not be as big of a risk as it sounds.
234
00:26:27,120.023694 --> 00:26:31,30.0197267
Okay, so maybe this gets into Monte Carlo and things like that.
235
00:26:31,450.0178956 --> 00:26:45,410.020337
But maybe you can talk about that, 'cause how do you actually, when you get down to brass tacks and you say, "Okay, what's the impact?" How do you quantify that? How does Monte Carlo fit in? What is Monte Carlo, Monte Carlo is a very interesting approach.
236
00:26:45,450.0212526 --> 00:27:18,790.0297975
If you think of it just at its at the core, if you have an activity and you have a 50% chance of finishing up on a day, and there's a dependent activity that you have a 50% chance of finishing it on, on, on time, you only have a, a 25% chance of meeting that, that schedule, right? So that's kind of what Monte Carlo is, is it says all these activities that you have in here, you've said that you've got a 10% chance of a risk occurring here, a 5% chance here, 25% chance here.
237
00:27:19,110.0218629 --> 00:27:33,356.025525
It goes through and- Does a thousand iterations of that schedule or that budget and says, "Okay, 10 of 10 of these or, you know, 100 of these, we're gonna apply this risk, and 200 of these we're gonna apply this risk."
238
00:27:33,766.0253724 --> 00:27:41,736.0244569
And then it cycles through the thousand iterations and says, "Okay, you have a 50% chance of meeting this number or this date."
239
00:27:42,346.0250673 --> 00:27:53,116.0236177
And so, The company has to make a determination whether they go with, that 50% chance number, the P50 as we call it,, or something more conservative like a P75.
240
00:27:53,116.0236177 --> 00:27:58,306.0222444
We have a 75% chance of coming in with this result, and therefore we're very confident we'll be within that.
241
00:27:58,916.0228547 --> 00:28:27,446.0192394
So the Monte Carlo just takes your cost estimate or your schedule estimate, runs through 1,000,, or, a count of your choosing iterations of that and applies the risks that you've identified where you've said they might impact that budget or schedule Do you do the Monte Carlo monthly or is that really pre-FID before you're making your final decision, you get that P50 and you're like, "That's good enough"? Like, how often- Yeah.
242
00:28:28,606.0190868 --> 00:28:37,306.0188961
Y- yeah, let me, let me back up a little bit and say Monte Carlo is most effective on large to very large projects.
243
00:28:37,816.018362 --> 00:28:45,756.0158443
A very small project, Monte Carlo is not nearly as effective, and you're not gonna get you know, the accuracy of the results that you would want to have.
244
00:28:46,276.0193539 --> 00:28:51,416.0187435
For smaller projects, we have the PERT method, the Pro- Program Evaluation Review Technique.
245
00:28:51,846.0182857 --> 00:28:53,846.0182857
That's what I recommend for smaller projects.
246
00:28:53,846.0182857 --> 00:28:55,596.0173702
Oh how do you present it? Yeah.
247
00:28:55,706.0179806 --> 00:29:08,926.0192013
So the inputs to a good Monte Carlo are an accurate up- updated budget or forecast, an accurate and updated schedule, and an accurate and updated risk register.
248
00:29:09,466.0201168 --> 00:29:13,616.0216427
So, you know, if you're doing those things monthly, you can run your Monte Carlo monthly.
249
00:29:14,386.0182857 --> 00:29:21,866.0262203
But Monte Carlo is, you know, you're typically talking about a very long timeline of the project, so you might not necessarily need it every month.
250
00:29:22,106.0240841 --> 00:29:26,56.0286617
So we, what we did on Leviathan was we did it approximately every quarter.
251
00:29:26,566.0231685 --> 00:29:30,46.0265255
We would update the Monte Carlo every month, but we would only present it every quarter.
252
00:29:31,26.022253 --> 00:29:31,456.0225582
Okay.
253
00:29:32,46.0265255 --> 00:29:38,166.0216427
And then when you say present, so risks are interesting, right? Because they I think oftentimes they can go all the way up to the board level.
254
00:29:38,396.0249996 --> 00:29:43,836.0283565
So you're surfacing a risk- down at this tiny little spot, and then it sort of bubbles up the organization.
255
00:29:44,166.0225582 --> 00:30:01,246.0060787
How does that work for, like, Leviathan, you, as the risk manager, do you present to, like, the project director, and the project director then presents up the chain? Is that typically how risks are surfaced, the project manager, project director, you know, they ultimately own all the risks.
256
00:30:01,276.004858 --> 00:30:06,506.0158443
You know, the risks should be individually owned by the people who are working to, to mitigate or close them out.
257
00:30:06,906.0097408 --> 00:30:09,66.0103512
But the project manager has final say on that.
258
00:30:09,66.0103512 --> 00:30:15,166.0298824
And so, yeah, we prepare the documentation for the project manager to present those items and those risks.
259
00:30:15,596.02561 --> 00:30:31,294.0124867
And then separately the risks that are assigned to people you know, as the risk lead, you're responsible for getting those updates from those people and making sure that, that the project manager is in alignment You're working, let's say Leviathan, right? So you've got your team.
260
00:30:31,374.0124104 --> 00:31:10,704.0198109
There's above you the risks are percolating kind of up through the org, right? Right there's also this sort of corporate b- barrier on big projects where a lot of times you have contractors that are doing major scopes of work, and so they have, how do you surface them from that part? 'Cause then you get this sort of like corporate boundary line, and those risks, like, how do you manage contractor risk, basically? Do you enforce it in the contract, or how does that work? What we tried to do is we would go directly to them, meet them at their office and tell them what we were doing, that we wanted to do a risk workshop with them.
261
00:31:10,704.0198109 --> 00:31:14,744.0169118
Could they bring what- whatever they were working from, whatever their risk registers were.
262
00:31:15,294.0199635 --> 00:31:23,554.0182851
And, you know, if, if we found deficiencies, we would just coach them and work with them to get them to do things the way that we preferred.
263
00:31:24,104.0196584 --> 00:31:30,194.0147755
But we found that most of our big contractors like that did have a risk management function and they were willing to meet with us to do that.
264
00:31:30,284.0156911 --> 00:31:34,4.0169118
So the risk manager is kind of a social animal, would you say, Lots of meetings.
265
00:31:34,684.0172169 --> 00:31:43,804.0254567
Yeah, and what's the right way, to approach those things? Because I feel like you can kind of be the almost like the tax man as a risk per- Feels like there's a few buckets.
266
00:31:43,844.0263722 --> 00:31:55,174.0205739
Either it's like, "Is this person helping me? Is this person draining my time?" Or, "Is this person going to get me?" And I feel like risk managers or risk conversations could fall into any of those buckets.
267
00:31:55,174.0205739 --> 00:32:08,554.0184377
So how do you disarm folks to have, to see you as like a helpful, good guy versus other- You know, my favorite, icebreaker is, you show up for a first meeting and say, "I'm from corporate.
268
00:32:08,584.0248463 --> 00:32:09,434.0233205
I'm here to help."
269
00:32:09,704.0199635 --> 00:32:11,744.0208791
And, you always get a bunch of laughter.
270
00:32:11,774.0208791 --> 00:32:12,944.0114186
Everybody finds that one funny.
271
00:32:12,944.0114186 --> 00:32:31,438.0183416
It's like I acknowledge that it, you guys don't wanna be here and you don't wanna hear from me, but, let's get through this and, and hopefully we'll see that we're adding some value to this activity So 'cause you're a personable guy, what can people do to work on those soft skills, do you have advice for someone that...
272
00:32:32,358.0184179 --> 00:32:40,848.0195242
'Cause it almost sounds like, a sort of math and science discipline of risk, and then there's this sort of social soft skill of risk.
273
00:32:40,848.0195242 --> 00:32:41,808.0186086
Like, how do people...
274
00:32:41,978.0186849 --> 00:32:47,178.0183035
The math and science, it's like ISO 3100, right? 30- Yeah, 31,000.
275
00:32:47,438.016625 --> 00:33:03,108.0147939
And then, but how do you develop the soft skills? Or are those in the ISO docs or, like, what do you recommend there? They're not in the ISO docs and, there's not a lot of very specific guidance in those frameworks, right? So, honestly I think it's, just a matter of getting your feet wet.
276
00:33:03,188.0158621 --> 00:33:04,38.0143362
Get in there and do it.
277
00:33:04,588.0173879 --> 00:33:19,918.019219
And yes, the first meeting and the first run-through is gonna be a little bit awkward people are kinda figuring out what you're doing, but after a couple of iterations it'll be a lot more natural and, everybody'll know what each personality is and it just gets easier.
278
00:33:19,918.019219 --> 00:33:22,268.0176931
So just get started, get going.
279
00:33:22,308.0186086 --> 00:33:23,318.0207449
It gets easier as you go.
280
00:33:24,238.0189138 --> 00:33:34,558.0216604
What's the one personality that's the most difficult, you would say, that you have to, like, manage right off the bat for risk? It's one end of the spectrum or the other.
281
00:33:34,558.0216604 --> 00:33:51,398.0155569
It's the everything is bad and is going to happen and you need to put 15 risks in your risk register for me, or none of that'll never happen so don't even put it in there, right? And you have to kinda talk them off the ledge and try to explain to them is why we're doing this.
282
00:33:51,398.0155569 --> 00:33:52,368.0091482
This is what we need to capture.
283
00:33:52,368.0091482 --> 00:33:57,508.0161672
It's not just about you, it's about future projects the project manager wants this, and report to the board."
284
00:33:57,508.0161672 --> 00:34:05,457.9987722
And so it's a, coaching and influencing activity for the ones that just kinda don't get it or, have an extreme view.
285
00:34:06,557.9972463 --> 00:34:08,767.9963308
So it sounds like there's sort of two ends of the spectrum.
286
00:34:08,767.9963308 --> 00:34:18,527.9938894
There's sort of the Pollyanna people, and then there's sort of this dooms- doomsayers, and Exactly sort of the center to moderate.
287
00:34:19,327.9969412 --> 00:34:19,667.9932791
Yeah.
288
00:34:20,77.9999929 --> 00:34:30,848.0042654
And th- those two are the ones that it's sometimes better to go meet with them in person out of the workshop and try to, you know, head off any of those types of outcomes.
289
00:34:32,354.0085378 --> 00:34:38,734.0085808
We've talked a ton about the soft skill, the, process of risk, things like that, kind of approaches.
290
00:34:39,404.008657 --> 00:34:43,394.0089622
One piece that I would love to get your perspective on is technology.
291
00:34:43,844.0097252 --> 00:34:45,824.0092674
I always say it's process before tool.
292
00:34:45,824.0092674 --> 00:34:47,304.0088096
We have discussed the process.
293
00:34:47,644.0089622 --> 00:34:56,474.0107933
But what's the role that good technology plays in risk management? And I guess I mean that from the, you were in the software side.
294
00:34:56,474.0107933 --> 00:34:59,424.0096489
You said you had a really great risk platform.
295
00:34:59,424.0096489 --> 00:35:07,24.008123
Like, how do you implement good technology solutions that actually help with this situation? Yeah.
296
00:35:07,504.0076652 --> 00:35:10,574.0073601
You know, it, it's, a- again, to go back to one is greater than zero.
297
00:35:10,574.0073601 --> 00:35:14,794.0098015
Having a risk register is i- infinitely better than not having one at all.
298
00:35:14,824.0085808 --> 00:35:24,24.0093437
And so, the s- somewhere far down the list is the what tool do you use? But the, the top of the list is create a risk register.
299
00:35:24,104.0111747 --> 00:35:24,414.0087333
That's it.
300
00:35:24,994.0105644 --> 00:35:32,284.0076652
You know, obviously Excel lends itself really well to doing that because you can, you specify what columns you want in the, in the spreadsheet.
301
00:35:32,814.0064445 --> 00:35:40,854.0073601
The main thing is to keep it simple for the, for especially for risk reviews and especially for the project teams and te- the leads.
302
00:35:41,374.0040031 --> 00:36:05,524.0064445
Keep it simple because, a fancy, complex tool sitting around a workshop is a, a big waste of their time, keep their time reviewing risks to focusing on exactly what they're supposed to be looking at and not, these, these big fancy, what's the risk velocity and what's the, we got a variety of other things that a lot of risk tools do that aren't necessary for a project.
303
00:36:06,24.0064445 --> 00:36:17,463.9948478
These very involved scientific risk studies, and risk reviews like failure mode effects analysis security vulnerability analysis pick one, HAZOPs, HAZIDs.
304
00:36:18,183.9960685 --> 00:36:28,263.9902702
Those are very specific and very detailed and very engineering-oriented, and they are not suited for project risk registers.
305
00:36:28,313.9902702 --> 00:36:32,143.9921013
The project risk register is the simplest form of risk review that exists.
306
00:36:32,143.9921013 --> 00:36:34,763.9872184
It's very basic, focused on project objectives.
307
00:36:34,763.9872184 --> 00:36:44,373.9750451
So you wanna use the simplest tool you can, especially when it comes to doing the reviews and workshops But you had a tool that you said was one of the best in the industry.
308
00:36:44,373.9750451 --> 00:36:53,433.9754361
Like, what was that doing that was so cool? That one was, was pretty cool because it did all of those methodologies in one single platform.
309
00:36:53,623.9750165 --> 00:37:01,833.9742917
So, we actually ended up using it and kind of customizing it a little bit to make it super simple for project risk registers.
310
00:37:02,253.973605 --> 00:37:10,753.9716977
But we would in many cases export that from that tool for a review because we only wanted a few fields from that risk register, while we were doing the review.
311
00:37:10,753.9716977 --> 00:37:14,93.9718503
So yeah, that's where the technology is important because you...
312
00:37:14,573.9752072 --> 00:37:32,1.9734518
if you choose too complex of a tool and it's too difficult to do that export and review or, you know, put it in a PowerPoint even then it just won't get done and it won't get updated and, and, you know, you'll have bad data in there So that was really like a point solution for people that were specialists.
313
00:37:32,321.9731466 --> 00:37:46,61.9748251
But when it actually came to communicating risk or trying to, like, assign s- like workflow related stuff was better managed in Excel rather than- Right having 20 people have a login to a risk tool that they have to, like, organize their risks in and all of that.
314
00:37:46,601.9757406 --> 00:37:47,431.973757
Exactly, yeah.
315
00:37:47,481.973757 --> 00:37:47,841.9743673
Okay.
316
00:37:48,521.9746725 --> 00:37:57,411.9740621
And did you find that was also the case when you were doing sort of a, a enterprise-wide multi-project portfolio as well, that you kind of allowed people to...
317
00:37:57,801.9734518 --> 00:38:11,511.976351
Did you roll a tool out for that, or did you also just kind of allow people to, to work one at a time? Y- we did roll a tool out, and by keeping it simple and training those risk champions in the various areas, we were able to drive usage of it, yes.
318
00:38:11,621.9743673 --> 00:38:18,341.9679586
But having those, those point contacts, risk champions, people who understood the process out in the field, that was very valuable.
319
00:38:19,231.9673483 --> 00:38:43,761.9517843
And was it like for that particular case, did you start with the training and then get the tool in place afterwards? Or was it like, "Here's a new tool," and you trained as you introduced the tool? There's always this kind of question of does it help to have a system kick off? We had the tool had it rolled out ahead of time but realized that we weren't getting the adoption that we wanted, which is when we developed the training to teach them the process.
320
00:38:44,131.9545309 --> 00:38:45,761.9517843
"And by the way, here's a tool you can use."
321
00:38:46,741.9551412 --> 00:38:47,191.9520895
Okay.
322
00:38:48,151.951174 --> 00:38:53,821.9557516
And then you and I have talked a little bit just to like zoom out, 'cause I feel like we're sort of, we're starting to go further out.
323
00:38:54,311.9566671 --> 00:39:04,761.9490377
I think you had, talked about how risk has been around for tens of thousands of years, that there's a,, a book that you recommended which maybe you could talk a little bit about.
324
00:39:04,761.9490377 --> 00:39:07,531.9456808
But when you actually get down to it, like risk is a very...
325
00:39:08,381.9517843 --> 00:39:14,251.942629
is something that humans have been dealing with for many of years, and now it's kind of sitting in ISO for projects.
326
00:39:14,671.940798 --> 00:39:33,515.9463093
Where do you see risk? What do you see as the, like, history of risk? Maybe you can teach us a little bit about that, and then where do you think risk as a discipline is going in the future? Once you have that risk management mindset, it kind of gives you a different perspective of things.
327
00:39:33,595.9460423 --> 00:39:42,295.9419987
It said something about how the lifecycle of a jet, it's, like 25 years for passenger service, after which it's only for cargo.
328
00:39:42,825.940778 --> 00:39:44,895.9442875
It's like, that's a risk mitigation.
329
00:39:45,125.9438298 --> 00:39:54,925.9384892
We're not gonna kill 300 people, we're only gonna kill two, you know? So you have a different perspective on life when you think of it from a risk management, aspect.
330
00:39:55,575.9392521 --> 00:40:00,335.9375737
But the book was the title is Against the Gods: The Remarkable Story of Risk.
331
00:40:00,925.9377263 --> 00:40:17,545.9328434
And it's very interesting because it talks about some of the early philosophers and how they loved to gamble because they understood what the odds were, and they were all about taking these low probability, high impact risks, gambling, trying to win something.
332
00:40:17,855.930402 --> 00:40:19,685.9322331
And, that's not all the book is about.
333
00:40:19,685.9322331 --> 00:40:20,675.9377263
It's a fascinating book.
334
00:40:20,725.9377263 --> 00:40:28,245.9419987
One of the things that I say is that the AI that we're using in 5 years or 10 years is going to be reading the data from today.
335
00:40:28,395.938947 --> 00:40:40,845.9358952
And so I feel like where risk management is going is leaning on AI to help us figure out what we need to be doing to avoid risks, not only in the project world, but, you know, broadly.
336
00:40:41,415.93559 --> 00:40:55,593.9331963
And I think that AI, but just like everything else is going to help with that focus on risk management and history and what has happened and good outcomes and bad outcomes, and how do we prevent that? How do you see...
337
00:40:55,673.93312 --> 00:41:31,673.935838
Is risk, like you run your Monte Carlo and then you also run your LLM,, is it sort of a new category of risk identification and forecasting? Like, how do you see this AI tools intersecting risk, like in a practical way? I think Monte Carlo was maybe sort of a rudimentary early, application of AI, right? Where it's saying we have the compute power to go through these cycles of, of trying to forecast what, what you think might happen.
338
00:41:32,323.9335492 --> 00:41:35,53.9330914
Whereas AI, I think would be a little...
339
00:41:35,393.933244 --> 00:41:48,193.9286663
will be, better at saying over the course of the life cycle of the project, you know, these things did or didn't occur, and therefore your Monte Carlo is changing in this way, or your potential outcomes are changing.
340
00:41:48,193.9286663 --> 00:42:01,405.9327236
And I think AI will outpace Monte Carlo as an approach to, you know, the, the potential outcomes of a project AI is like a super Monte Carlo.
341
00:42:01,545.933067 --> 00:42:15,225.9342304
Right markov chains are kind of like, chained together tokens where you're like, "This is probabilistically connected to this, that's connected to this," and then you zoom that up into trillions of connections.
342
00:42:15,655.9326283 --> 00:42:26,165.9347645
And so that's kind of like if you took your risk register and then you broke it into tokens, which would be like words, and then had probabilities that...
343
00:42:26,415.9347645 --> 00:42:44,485.9344593
You know, instead of Monte Carlo having a schedule that has like 10 dependencies that it's running it on, an LLM is looking at those tokenized values and running it against trillions of connected points to like suss out probabilistic outcomes.
344
00:42:44,485.9344593 --> 00:42:49,165.9347645
So it really does seem like, yeah, maybe it is like a super Monte Carlo in a way.
345
00:42:49,215.9347645 --> 00:42:59,665.9385792
Yeah, and the Monte Carlo is very dependent on the quality of the inputs, whereas with AI I feel like, you can be a little softer on that quality and still have a good outcome.
346
00:42:59,665.9385792 --> 00:43:05,755.9394947
And also I think it's easier to look across other projects with an LLM than it is to, today's software.
347
00:43:06,885.9397999 --> 00:43:12,155.936443
Do you see as the downside of this AI in risk? Obviously hallucinations, things like that.
348
00:43:12,155.936443 --> 00:43:21,725.9361378
Is there some dangers that the future holds? I still think for a lot of project scope y- you have to have the expert opinions.
349
00:43:21,825.9376637 --> 00:43:26,445.9425465
AI can do a lot but, you need people who have the experience and, and have been through it.
350
00:43:27,75.9385792 --> 00:43:37,505.9388844
I don't think for some project disciplines that there is a, you know, near to midterm risk of anything going away for, for them.
351
00:43:37,545.9397999 --> 00:43:46,685.9489552
I believe those skills and experiences are, are important to have, and the- it'll be a, a long time before those are impacted by AI in my opinion.
352
00:43:48,381.9471337 --> 00:43:49,191.9470764
So what's your...
353
00:43:49,241.9472672 --> 00:44:00,711.947744
Are you thinking we're probably 50 to 100 years away from just robots building everything and doing their own risk registers and- Once we're fully globalized, right? I say that because who knows what the future holds.
354
00:44:00,711.947744 --> 00:44:07,41.9476677
I mean, just the last couple of years of technology, you know, seems like w- we've made some pretty big leaps.
355
00:44:08,261.9481255 --> 00:44:13,761.9511772
Let's say that I'm a project director and I just hired a risk manager for a mega project.
356
00:44:14,711.9519402 --> 00:44:40,777.9516069
What advice would you give that project director to enable that risk manager and get their risk going? Like, what am I doing to help the risk situation? If that person is starting from scratch obviously we need to know wh- who to talk to make those connections, establish those relationships, get to know the leads of the various disciplines that'll be working on the project, if those are known at the time.
357
00:44:41,327.950844 --> 00:44:44,747.9490129
But yeah, certainly develop those relationships as early as possible.
358
00:44:45,747.9490129 --> 00:44:46,37.9499284
Okay.
359
00:44:46,37.9499284 --> 00:44:48,327.950844
I'm vice president of this company.
360
00:44:48,617.9479448 --> 00:44:50,967.9502336
We're gonna take on this mega project.
361
00:44:51,27.9477922 --> 00:44:53,877.950081
We just FID'd or we're a little bit into it.
362
00:44:54,127.950081 --> 00:45:04,717.9502336
How do I know if risk is actually being managed well? What are the signals that I could see where I'm like, "We probably have a risk problem we need to, like, figure it out," or, "This is excellent.
363
00:45:05,127.950081 --> 00:45:17,117.937874
Risk is running really well in my organization"? What would you advise someone like that to look for? As long as they are very well aware of the risks of their various projects, I would say it's running well.
364
00:45:17,147.9366533 --> 00:45:26,497.9427568
One of the main things that I encourage people to do is to describe Risk in a way that it can be understood by someone who has nothing to do with the project.
365
00:45:27,67.9424516 --> 00:45:27,597.9412309
Okay.
366
00:45:28,617.937874 --> 00:45:35,567.9271928
So, they need to understand exactly what that risk is, not just $10 million.
367
00:45:35,567.9271928 --> 00:45:42,357.9281084
We have to say what that risk is and it has to be described in a way that is meaningful for outside parties.
368
00:45:43,537.9284135 --> 00:45:43,847.9259721
Okay.
369
00:45:43,937.9299394 --> 00:46:06,37.9284135
So if I'm an executive and I'm, I'm s- looking at this project and I get the risk register out, and it's highly technical stuff where I'm like, "I could not hand this to an investor or somebody else, and they would have no idea what's going on here," that's probably- Correct a flag that you wanna you wanna take a harder look at risk and, and maybe level up a little bit for the organization.
370
00:46:06,507.932686 --> 00:46:18,57.920479
Absolutely what if I'm on a project and I wanna be I'm like a scheduler or an engineer or someone in the field, and I wanna be good for the risk manager.
371
00:46:18,57.920479 --> 00:46:50,757.9176513
Like, what advice would you give them to support this new risk manager that started, Always analyze inputs into your, your cost or your schedule with a little bit of skepticism, and ask questions to try to make sure that you as a, as the scheduler or, or as the, cost control person, also buy into that result and, and you know what the risks are, and you know that they have been identified and/or mitigated.
372
00:46:51,207.9184143 --> 00:46:51,487.9210083
Okay.
373
00:46:52,297.9185669 --> 00:47:06,917.9283325
And then I guess one last thing if I'm starting a new project, should I insource or outsource risk? What's the, what's the cost benefit on that? Because a lot of big orgs, they just sort of have a outsourced risk function, and some people bring risk in-house.
374
00:47:07,357.9269592 --> 00:47:14,117.9290954
Do you have a strong preference or opinion on that? I found it to be pretty effective to be insourced.
375
00:47:14,357.9269592 --> 00:47:17,267.9229919
Obviously, not everybody can or, or wants to do that.
376
00:47:17,297.9217712 --> 00:47:23,577.9281799
And certainly with risk management, if it's not very well understood in the organization, it might be more effective to outsource it.
377
00:47:25,17.9229919 --> 00:47:30,107.9300109
Certainly I, I have a little bit of a bias that I can recognize there that, it worked really well by insourcing it.
378
00:47:30,637.9287902 --> 00:47:53,757.9269592
But I, I would just say, you know, again, a- a- all of those key things, making sure that, that whoever the person is that's doing it, especially if it's outsourced, that you know that they're meeting with those key, individuals, key contractors, discipline leads, having regular meetings, having regular updates, and describing risk in a way that your organization can understand it, not just the risk manager.
379
00:47:54,307.9223816 --> 00:47:56,127.9220764
Y- you can have success either way.
380
00:47:57,757.9193298 --> 00:47:58,27.9236023
Okay.
381
00:47:58,727.9205505 --> 00:48:22,103.9201507
Is there a single takeaway that you would love for someone to get from our conversation? What do you think is the most important thing or one of the most important things that you'd like them to remember or that we could highlight? I would say there are a couple of key concepts in risk management that have always stuck with me.
382
00:48:22,103.9201507 --> 00:48:26,423.921524
One of them I, I said a little bit ago a lesson learned is a risk on a future project.
383
00:48:26,463.9205322 --> 00:48:28,953.9203033
I feel like lessons learned are extremely important.
384
00:48:29,483.9209899 --> 00:48:36,983.9209899
Whether you call them that or not, you know, even an old risk register is a lessons learned register, right? You've captured a number of lessons learned there.
385
00:48:36,983.9209899 --> 00:48:40,413.9193878
So, risk, lesson learned is risk on a future project.
386
00:48:40,993.9212188 --> 00:48:48,753.9195403
And then another one that I found in an old Navy training slide deck was change is the mother of all risk.
387
00:48:49,963.9224395 --> 00:48:50,73.9192352
Okay.
388
00:48:50,73.9192352 --> 00:49:05,193.9190826
And if you think about that, as a concept, a lot of times when you have bad outcomes, it can be traced back to some kind of a change or a decision or something that we did differently than we had originally planned.
389
00:49:05,853.91893 --> 00:49:16,156.917037
And so anytime there's any talk of change, that, that should be a risk conversation change is the mother of all risks.
390
00:49:16,506.9169416 --> 00:49:21,136.9174947
It, kind of gets back into how time is always required for risks.
391
00:49:21,136.9174947 --> 00:49:21,356.9177617
Right.
392
00:49:21,726.9176473 --> 00:49:22,176.9174566
Yeah.
393
00:49:22,356.9177617 --> 00:49:22,536.9171132
Yeah.
394
00:49:22,736.9169225 --> 00:49:23,76.9170751
It's...
395
00:49:23,526.9170751 --> 00:49:28,266.9168462
and the, and the whole CUSO concept, right? This is your outcome, and any deviation from that is a risk.
396
00:49:28,906.9181432 --> 00:49:29,286.917304
Yeah.
397
00:49:30,186.9169225 --> 00:49:49,36.9153966
So what advice would you give if someone's listening to this and they're in college and they wanna go become a risk manager? Do you have advice for someone that might be pursuing a career? Just keep in mind that project risk management is the simplest form of risk methodologies that exists.
398
00:49:49,96.9129552 --> 00:49:59,966.9149389
It's very basic, that the simpler you approach it, the more success you'll have and the easier it will be to replicate that success over time, especially over the life cycle of a project.
399
00:50:00,486.9153966 --> 00:50:01,306.9150915
Keep it simple.
400
00:50:01,616.9147863 --> 00:50:07,736.9137182
Don't overanalyze the, all the Google results that are out there that tell you what project risk management should be.
401
00:50:07,736.9137182 --> 00:50:08,896.9173803
It's, it's very basic.
402
00:50:09,916.9216527 --> 00:50:16,836.9200601
But how do you get a job in risk? So there are, there are jobs open currently for project risk managers.
403
00:50:16,866.9197931 --> 00:50:18,336.9200601
That does exist as a role.
404
00:50:18,446.9204034 --> 00:50:29,436.9201745
Typically, it's within, like, an EPC-type company, and they're working across multiple projects, which means that that company is trying to, have a, a discipline across every project that is risk management.
405
00:50:29,496.9198694 --> 00:50:31,166.9199457
Kind of everything we described today.
406
00:50:31,246.9206323 --> 00:50:32,336.9207849
Those jobs exist.
407
00:50:32,846.9210138 --> 00:50:33,726.9201745
You know, you, you...
408
00:50:34,266.9203271 --> 00:50:39,896.9194879
it's, sometime easier to move into that role once you're within a company and are working on a project.
409
00:50:40,296.9181146 --> 00:50:43,486.9167413
That sometimes is a, a good approach to getting into that role.
410
00:50:43,486.9167413 --> 00:50:44,996.9150628
It's kind of how I found myself there.
411
00:50:45,986.9167413 --> 00:50:47,426.9191827
So it's sort of a lateral move.
412
00:50:47,426.9191827 --> 00:50:53,206.917962
You sort of start on these projects and then make your way into the risk space when a opportunity opens up.
413
00:50:53,996.9181146 --> 00:50:54,286.9152154
Yeah.
414
00:50:54,686.9159784 --> 00:51:05,606.9133844
If you're really into risk management as a discipline you, you'll know it, right? But, for an organization that recognizes the value of that, they love to have people in those types of roles.
415
00:51:06,336.9167413 --> 00:51:12,526.9191827
If I'm that student, how do I sense-check that myself? Like, let's say I'm, like, an engineer, I'm thinking about risk.
416
00:51:12,566.9200982 --> 00:51:13,866.9155206
Maybe that's where I wanna go.
417
00:51:14,356.9133844 --> 00:51:16,866.9155206
But then I'm like, "You know what? I really don't like working with people."
418
00:51:16,926.9130792 --> 00:51:20,996.9204034
You know, I think from our conversation we'd know, okay, that your profile might not actually enjoy this.
419
00:51:20,996.9204034 --> 00:51:23,176.9207086
Or what's something students could think about to, like...
420
00:51:24,266.9200982 --> 00:51:30,486.9213189
someone who's very curious and loves to always be learning, because every project Is different.
421
00:51:30,546.9188775 --> 00:51:32,206.9225396
The scope of the project is different.
422
00:51:32,206.9225396 --> 00:51:53,116.919101
Materials are different, right? So you always have to think through what is different about this project? What risks might I have? What have I not thought of yet? So it's like if you're considering a job in patent examining, you might want, think about risk too, right? Like just being able to be on a continual learner as well.
423
00:51:53,116.919101 --> 00:51:53,176.9195206
Yeah.
424
00:51:53,176.9195206 --> 00:51:56,116.9200547
It sounds like you have to kind of have that curiosity.
425
00:51:56,116.9200547 --> 00:52:07,596.9203598
I've heard it said that,, you know, a project manager might work on three projects in their career but when you're talking about a risk manager, you, you are likely going to work on dozens of projects.
426
00:52:08,716.9211991 --> 00:52:17,336.9247086
Well, is there any books or industry associations that you would recommend? We talked about Against the Gods: The Remarkable Story of Risk.
427
00:52:17,786.9247086 --> 00:52:22,296.9230301
Any other sort of resources out there or things that...
428
00:52:22,606.9244034 --> 00:52:31,626.9240982
podcasters you follow, anything that other people could go deeper with? I would say the Project Management Institute guidance on risk management is really good.
429
00:52:32,46.9253189 --> 00:52:33,56.9274552
It's applicable.
430
00:52:33,326.9279129 --> 00:52:42,586.9247086
There are some concepts in there that are, maybe a little more advanced for some projects, and it tries to be, all-encompassing every type of project.
431
00:52:42,696.9253189 --> 00:52:47,66.9311173
But that's good guidance and it's specific to projects.
432
00:52:47,66.9311173 --> 00:52:48,696.9329483
So that's kind of where I would start.
433
00:52:49,196.9283707 --> 00:52:50,956.9305069
I mentioned ISO 31000.
434
00:52:51,506.9335587 --> 00:53:02,966.9402726
That is a framework and it's more geared toward corporate-type risk management implementation, so I wouldn't say let that be too much of an influence other than to say that there's a process that should be followed.
435
00:53:03,506.9366104 --> 00:53:04,886.9414933
Same with COSO ERM.
436
00:53:05,266.9417984 --> 00:53:16,116.9402725
Another good reference is, I believe it's ISO Guide, I think it's 73, but it's all of the definitions of terms around risk management.
437
00:53:16,366.9402725 --> 00:53:21,286.939357
The one I gave about the definition of risk, that's from the ISO Guide, I think the number is 73.
438
00:53:21,286.939357 --> 00:53:23,46.9338639
That's another good one to get familiar with.
439
00:53:24,486.9363053 --> 00:53:24,996.9384415
Cool.
440
00:53:25,376.9387467 --> 00:53:41,696.9308121
Is there any conferences that people go to on risk that are really good to go into or surface? Is it really the PMI conference or is there like little niche risk people association? Yeah, I mean, there, there's all kinds of stuff on LinkedIn that you can find.
441
00:53:41,796.9338639 --> 00:53:50,296.9186051
Risk can mean so many different things and project risk is, is a very specific discipline within that larger risk concept.
442
00:53:50,976.9112809 --> 00:53:58,326.9021256
But things like IPA and project analysis, they do a lot of, of project specific focus on risks.
443
00:53:58,326.9021256 --> 00:54:01,116.8832047
So any kind of IPA conference you can attend, I would encourage.
444
00:54:01,846.8789322 --> 00:54:06,186.8752701
Matt, I really appreciate you joining us, sharing all of your wisdom.
445
00:54:06,186.8752701 --> 00:54:14,540.8712259
Is there any other tips or tricks you want to leave us with before we wrap up? That's one thing we didn't talk about just the terminology.
446
00:54:14,590.8714166 --> 00:54:23,460.8703485
Settle on a set of definitions, and just know that people will have experienced other terms that meant the same thing.
447
00:54:23,940.8717981 --> 00:54:24,240.8710351
Mm-hmm.
448
00:54:24,240.8710351 --> 00:54:31,460.8695855
Like severity or impact, right? Those kind of mean the same thing or in a risk management, in, in risk management terminology.
449
00:54:31,980.8700433 --> 00:54:36,240.8721795
But just define what all those terms are for your project and for your program.
450
00:54:37,760.8688226 --> 00:54:46,400.8689752
Going back to, like, having a singular perspective is really important- Right because if you have two different scales that you're measuring things against, doesn't work at all.
451
00:54:46,710.8695855 --> 00:54:56,900.871264
Do you send out that appendix to everybody before as, like, a prep activity? Or how do you actually get that front and center? We build it into the guideline documentation.
452
00:54:57,70.869433 --> 00:55:00,620.86867
So anyone who's curious enough to read that would, would see it.
453
00:55:01,40.8698907 --> 00:55:11,790.8734002
But yeah, at, at a workshop, we typically would have a series of handouts, your risk ra- risk, matrix so, you know, people are, are grading their risk, they know what they're working from.
454
00:55:11,790.8734002 --> 00:55:14,190.8791986
And then, you know, terminology, definitions.
455
00:55:14,980.8801141 --> 00:55:16,700.8825555
Well, Matt, thank you for joining us today.
456
00:55:16,700.8825555 --> 00:55:21,360.8862176
I was- learned so much, about Leviathan, kind of your role in that.
457
00:55:21,750.8856073 --> 00:55:29,390.883471
We went deep on the high end of risk with Monte Carlo and down to the low, sort of just conceptual definition of it.
458
00:55:29,390.883471 --> 00:55:32,120.886828
I, I can't thank you enough for taking us through this.
459
00:55:32,160.8877435 --> 00:55:37,990.8926263
Sure appreciate your time today, and hope that we get to chat with you again about this important topic.
460
00:55:38,870.8907953 --> 00:55:39,440.8904901
I appreciate it.
461
00:55:39,470.8892694 --> 00:55:40,210.8871331
Thanks for your time as well.