Auckland’s $5.5 billion City Rail Link (CRL) will not open until sometime in 2026 or later, the Herald can reveal.
This is at least 18 months longer than what was forecasted only a few months ago when the cost of the project blew out by $1.1b to $5.5b and the completion date moved from late 2024 to November 2025.
In an exclusive interview during a tour of the mega-project, City Rail Link chief executive Dr Sean Sweeney said the latest completion date is not when Aucklanders will get to ride the underground railway.
He said November 2025 is when City Rail Link Ltd hands over the brand spanking new 3.4-kilometre track from Britomart to Mt Eden to Auckland Transport and KiwiRail, which then have to do extensive testing before it opens to passengers.
Sweeney was reluctant to say how long that could be, but when pressed said: “As a ballpark guess, I’d say six months, but people need to understand that numbers could change a lot, based on what happens.”
The big issue vexing the minds of Sweeney and the Alliance contractor is moving from the construction of the tunnels and stations to the complex and risky phase of installing bespoke software and signalling work, and plugging a state-of-the-art railway into the existing, fault-ridden network.
Three years ago, Sweeney told the Herald there are going to be challenges at the “back end”, and the problem is made worse because a metro rail system has never been built in New Zealand.
At the time, he was commenting on the Crossrail line under London that encountered massive and costly overruns after back-end problems just as everyone was doing victory laps - the chairman got a knighthood and later got sacked.
Sweeney said Crossrail was a much more complex project and does not envisage similar problems with the CRL, but did acknowledge plugging new plants and equipment into the existing rail network could lead to “unintended consequences”.
Full testing of the new systems is expected to begin in mid-2024 and will take about a year, said Sweeney, who is planning to finish the job before the November 2025 date.
One of the biggest issues that needs testing, he said, is a fire on a train in the tunnel.
After the handover, AT and KiwiRail have to go through another set of tests, which Sweeney said is not straightforward and involves a lot of operational and training exercises.
“There are exhaustive tests that they will have to go through, and safety checks, before they are allowed to run passengers,” Sweeney said.
For example, every one of the 240 drivers in Auckland will have to go through the tunnels for training.
An AT spokeswoman could not say when trains will start running on the CRL, saying it is working with CRL Ltd and the Alliance contractor, Auckland One Rail, the rail safety regular Waka Kotahi New Zealand Transport Agency and other stakeholders on a plan to begin as early as possible.
The plan involved critical testing of the new systems before trains can operate, including emergency and evacuation protocols, driver training, signalling and other important systems needed to operate the CRL safely.
“We will be able to confirm the dates for CRL operations once this programme is complete,” she said.
Artist's impression of what the Karanga-a-Hape station will look like once it opens. Photo / Supplied
Auckland Chamber of Commerce chief executive Simon Bridges, w
Stuff You Should Know
If you've ever wanted to know about champagne, satanism, the Stonewall Uprising, chaos theory, LSD, El Nino, true crime and Rosa Parks, then look no further. Josh and Chuck have you covered.
Dateline NBC
Current and classic episodes, featuring compelling true-crime mysteries, powerful documentaries and in-depth investigations. Follow now to get the latest episodes of Dateline NBC completely free, or subscribe to Dateline Premium for ad-free listening and exclusive bonus content: DatelinePremium.com
24/7 News: The Latest
The latest news in 4 minutes updated every hour, every day.