Story by Audrey Brice
The Cleave Street redevelopment project has been a key part of the Estes Park Downtown Plan since its conception in 2018. The purpose of the project has been to transform what has been an underutilized alley into a pedestrian-friendly corridor. However, delays and disruptions have frustrated some local business owners with the process.
According to Jamin Rucker, a civil engineer in the public works department, the Cleave Street project was scheduled to begin in spring 2024, but was postponed to allow utility companies time to complete the undergrounding of all overhead services. At the request of citizens and nearby business owners, the project’s start date was further delayed to avoid construction during the summer and fall of 2024.
A major, unforeseen challenge that delayed the completion of Cleave Street was the discovery of a shallow utility duct bank containing phone and cable lines owned by CenturyLink/Lumen. According to Rucker, these lines conflicted with the planned concrete depth in two sections totaling about 350 feet along Cleave Street.
The duct was identified before construction began, but the information at that time suggested it would be buried deep enough to avoid interference. The issue was uncovered in late December 2024 and took around three months to fully resolve, halting work in that area during that period.
“Minor delays are anticipated and addressed throughout all projects, but this situation was unique,” said Rucker. “We are grateful for ABC Asphalt’s ability to adapt to this unforeseen circumstance on Cleave Street this past winter. They remained productive in other areas to keep the project on schedule as much as possible.”
According to Rucker, it has been difficult to predict a completion date for the project, citing disruptions including available supply of materials and fairly constant spring thunderstorms that slowed the project’s progress.
“We have reopened Cleave Street Friday through Sunday and hope to have the road fully open to all traffic very soon,” said Rucker. “Some minor tasks, such as the installation of benches and protective bollards for the new electric transformers, may not be completed until the third week of June.”
Rucker noted that this week, ABC was working to finish concrete removals where the street has cracked and where the heated drain pan must be replaced at the west end of the street. He added that final tasks for the project include decorative stonework on the landscaping walls, sealing concrete expansion joints to waterproof them, landscaping, and installing benches, bollards, and trash receptacles.
The original budget for Cleave Street’s redevelopment was approximately $3.1 million, with a low bid of just under $2 million. Although unexpected costs have arisen, certain contract items were removed to control expenses. Town officials expect final costs to remain within the contract amount and significantly below the initial budget.
For businesses near Cleave Street, project delays have been frustrating. Mark Igel, owner of The Taffy Shop and Town Board Trustee, expressed frustration with limited access to his businesses and the unpredictability of the project schedule.
“That construction has been very difficult for us with access to the business,” said Igel. “It has impacted us by making it hard to get to the property. As a business, so far, the impact has been entirely negative.”
Despite frustrations, Igel acknowledges the efforts of those involved in the project to accommodate businesses impacted by the construction.
“I think it’s really important to recognize their efforts above and beyond to help us with that. They have provided heavy equipment to move in heavy deliveries. They’ve helped us with the big things that we need to move in and out,” said Igel.
Read full story here:
On Purpose with Jay Shetty
I’m Jay Shetty host of On Purpose the worlds #1 Mental Health podcast and I’m so grateful you found us. I started this podcast 5 years ago to invite you into conversations and workshops that are designed to help make you happier, healthier and more healed. I believe that when you (yes you) feel seen, heard and understood you’re able to deal with relationship struggles, work challenges and life’s ups and downs with more ease and grace. I interview experts, celebrities, thought leaders and athletes so that we can grow our mindset, build better habits and uncover a side of them we’ve never seen before. New episodes every Monday and Friday. Your support means the world to me and I don’t take it for granted — click the follow button and leave a review to help us spread the love with On Purpose. I can’t wait for you to listen to your first or 500th episode!
Crime Junkie
Does hearing about a true crime case always leave you scouring the internet for the truth behind the story? Dive into your next mystery with Crime Junkie. Every Monday, join your host Ashley Flowers as she unravels all the details of infamous and underreported true crime cases with her best friend Brit Prawat. From cold cases to missing persons and heroes in our community who seek justice, Crime Junkie is your destination for theories and stories you won’t hear anywhere else. Whether you're a seasoned true crime enthusiast or new to the genre, you'll find yourself on the edge of your seat awaiting a new episode every Monday. If you can never get enough true crime... Congratulations, you’ve found your people. Follow to join a community of Crime Junkies! Crime Junkie is presented by audiochuck Media Company.
Ridiculous History
History is beautiful, brutal and, often, ridiculous. Join Ben Bowlin and Noel Brown as they dive into some of the weirdest stories from across the span of human civilization in Ridiculous History, a podcast by iHeartRadio.